HOW TO APPLY PERMITS (BUILDING, ELECTRICAL AND PLUMBING) FOR RESIDENTIAL BUILDING WITH FLOOR AREA 20 SQ.M. BELOW AND TOTAL PROJECT COST AMOUNTING TO P15,000.00 AND BELOW

Created: 10 November 2015 Published Date Hits: 950

ISSUANCE OF PERMITS (BUILDING, ELECTRICAL AND PLUMBING) FOR RESIDENTIAL BUILDING  WITH FLOOR AREA 20 SQ.M. BELOW AND  TOTAL PROJECT COST AMOUNTING TO P15,000.00 AND BELOW

Who May Avail of the Service:

Any person, firm, or corporation including any agency or instrumentality of the government who intend to construct a building/structure

Where to Transact: Building & Industrial Safety Section, City Engineer’s Office

Person In-charge:            Engr. Darwin S. Arig

                                       City Engineer

What are the Requirements:

  • Clearance/Certification:
    • Barangay Construction Clearance
    • Zoning Certification
    • Locational Clearance
    • Mayor’s Certification
    • Fire Safety Certification
    • PALC if the structure constructed within the subdivision area
  • If the applicant is the owner of the lot
    • Land Title (Photocopy)                                           
    • Latest Tax Declaration (Photocopy)                                           
    • Latest Tax Clearance (Photocopy)                                 
    • Official Receipt                                                                        
  • If the applicant is not the owner of the lot                               
    • Deed of Sale (Photocopy)                                                        
    • Deed of Donation (Photocopy)                                             
    • Extrajudicial Partition (Photocopy)                                    
    • Lot Owner’s Consent (Notarized optional)                                                                                                    

Plans:

  1. Sketch Plan (Electrical Plan)  Signed and Sealed by Professional Electrical Engineer
  2. Sketch Plan (Building) Not necessary the signature of the Civil Engineer
  3. Bill of Materials and Cost Estimate

Duration: Three (3) working days

Schedule of Availability of Service:

Monday – Friday

8:00am – 5:00pm; no noon break

 

How to Avail the Service:

Step

What To Do

To Whom

Action To Take

1

Secure application form and checklist of requirements

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

 

Arman A. Aquino

Electrical Inspector II

 

Anastacio R. Alcantara

Electrical Inspector II

Ø Provide Application Form and checklist of requirements to the applicant

 

2.

Submit the application with the complete requirements and wait while the documents are being evaluated.

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

Ø Receive and evaluate the application as to completeness of the requirements.

If incomplete, return the documents to the applicant

3

 

Engr. Eric C. Palacio

Engr. Alexander R.  Rulete

Engr. Alexander R.  Rulete

Aquilino C. Batindaan

Aquilino C. Batindaan

Ø Receive and record the application and advise the applicant to follow-up within 2 days. The application is subject for detailed evaluation as to the following aspect.

1.Line & Grade

2. Land Use & Zoning

4. Structural

5. Sanitary

6. Electrical

4.

 

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

Ø Assessment of Fees

 

5

Pay at City Treasurer’s Office and submit the Official Receipt to the Building & Industrial Safety Section

 

 

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

 

Arman A. Aquino

Electrical Inspector II

 

Anastacio R. Alcantara

Electrical Inspector II

Ø Receive and record the official receipt

 

6

 

Engr. Alexander R. Rulete

Building Inspector

Ø Final review and recommendation

7

 

Engr. Darwin S. Arig

City Engineer

Ø Approval

 

8

Receive the copy of approved permit and signify in the logbook.

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

 

Arman A. Aquino

Electrical Inspector II

 

Anastacio R. Alcantara

Electrical Inspector II

Ø Receive, record, number and release the approved permit.