HOW TO APPLY PERMITS FOR BUILDING, ELECTRICAL, PLUMBING AND MECHANICAL (FOR TOWER/SIGNAGES)

Created: 10 November 2015 Published Date Hits: 2636

ISSUANCE OF PERMITS (BUILDING, ELECTRICAL, PLUMBING AND MECHANICAL)

FOR TOWER/SIGNAGES

Who May Avail of the Service:

Any person, firm, or corporation including any agency or instrumentality of the government who intend to construct a Tower/Signages

Where to Transact: 

Building & Industrial Safety Section, City Engineer’s Office

Person In-charge:         

Engr. Darwin S. Arig - City Engineer

 

What are the Requirements:

  • Clearance/Certification
    • Barangay Construction Clearance
    • Zoning Certification
    • Locational Clearance
    • Mayor’s Certification
    • Fire Safety Certification
    • Environmental Compliance Certificate (ECC) for tower
    • ATO Clearance for tower
    • Radiation Clearance from DOH for tower
  • If the applicant is the owner of the lot
    • Land Title (Photocopy)                                                 
    • Latest Tax Declaration (Photocopy)                                           
    • Latest Tax Clearance (Photocopy)                                             
    • Official Receipt                                                                        
  • If the applicant is not the owner of the lot                               
    • Deed of Sale (Photocopy)                                                        
    • Deed of Donation (Photocopy)                                                 
    • Extrajudicial Partition (Photocopy)                                            
    • Lot Owner’s Consent (Notarized)                                               

Plans:

  • Duly accomplished application Form
    1. Building Plan Signed and Sealed by Civil Engineer/Architect
    2. Electrical Plan Signed and Sealed by Professional Electrical Engineer
    3. Plumbing Plan Signed and Sealed by Master Plumber/Sanitary Engineer
    4. Mechanical Plan Signed and Sealed by Professional Mechanical Engineer
    5. Bill of Materials and Cost Estimate Signed and Sealed by Civil Engineer/Architect
    6. Structural Design and Analysis Signed and Sealed by Civil Engineer
    7. Specification Signed and Sealed by Civil Engineer/Architect

 

Fees: It is based on the revised IRR of PD1096  National Building Code of the Philippines

Duration: Three (3) working days

Schedule of Availability of Service:

Monday – Friday

8:00am – 5:00pm; no noon break

 

How to Avail the Service:

Step

What To Do

To Whom

Action To Take

1

Submit the application with the complete requirements and wait while the documents are being evaluated.

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

Ø Receive and evaluate the application as to the completeness of the requirements.

If incomplete, return the documents to the applicant

2

 

Engr. Eric C. Palacio

Engr. Alexander R.  Rulete

Engr. Alexander R.  Rulete

Aquilino C. Batindaan

Aquilino C. Batindaan

Engr. Samson Corpuz

Ø Receive and record the application and advise the applicant to follow-up within 2days. The application is subject for detailed evaluation as to the following aspect.

  1. Line & Grade
  2. Land Use & Zoning
  3. Structural
  4. Sanitary
  5. Electrical
  6. Mechanical

3

If no error in the plans & specs, the document is subject for final assessment of fees.

 

 

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

 

Arman A. Aquino

Electrical Inspector II

 

Anastacio R. Alcantara

Electrical Inspector II

Ø Assessment of Fees

 

4

Pay at City Treasurer’s Office and submit the Official Receipt to the Building & Industrial Safety Section.

 

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

 

Arman A. Aquino

Electrical Inspector II

 

Anastacio R. Alcantara

Electrical Inspector II

 Ø Receive and record the official receipt

 

5

 

Engr. Alexander R. Rulete

Building Inspector

Ø Final review and recommendation

6

 

Engr. Darwin S. Arig

City Engineer

Ø Approval

7

Receive the owner’s copy and signify in the logbook.

Anyone of the following:

Engr. Alexander R. Rulete

Building Inspector

 

Aquilino C. Batindaan

Building Inspector

 

Ricky A. Calago

Building Inspector

 

Arman A. Aquino

Electrical Inspector II

 

Anastacio R. Alcantara

Electrical Inspector II

Ø Receive, record, number and release the approved permit.